Thank you for subscribing to updates related to the National Energy Code of Canada for Buildings (NECB) and Section 9.36 of the Alberta Building Code (ABC), both of which come into force on Nov. 1, 2016. These notifications will provide technical code interpretations, and aim to inform those who design and construct buildings in Calgary.

These updates will also be available on our website at calgary.ca/energycode and calgary.ca/936.
Update

Code article
NECB Div. A-1.1.1.1.(1) Application of this code
Except as provided in Sentence (2), this code applies to the design and construction of all new buildings described in Sentence 1.3.3.1.(1) of Division A of the NECB and to additions.

Previous direction
None
 
Current direction
There is little guidance in the NECB on compliance options for buildings of seasonal, temporary or movable/removable construction. These include:
  • Greenhouses
  • Tents and air supported structures
  • Portables and re-locatable structures
  • Show suites/sales centres
Temporary buildings
Buildings may be exempt from the requirements of the NECB if it will have an occupancy duration of one year or less. Temporary permits seeking exemption from NECB requirements will not be granted extensions.

Temporary permit exemptions as stated above apply to all building types regardless of use, including greenhouses, sales centres and tents/air supported structures.
 
Seasonal and special use buildings
In considering building types that may have energy efficiency parameters not envisioned by the NECB, the requirements of this code may be exempted for a whole or part of a building. This may be broadly interpreted to also include building subsystems.

All portions of a building that are deemed to be within the scope of the NECB should be made to comply with the NECB.
 
Compliance summary of some typical special use and re-locatable structures:
Building use/type Envelope
NECB Part 3
Lighting
NECB Part 4
HVAC
NECB Part 5
Service water heating
NECB Part 6
Greenhouses (not within a permanent building enclosure) Exempt greenhouses from NECB envelope requirements as farm buildings. Related offices, service areas, etc. must comply. Comply Comply Comply
Tents,
air-supported and
sprung type structures
Exempt tents and similar structures from envelope requirements per NECB 3.1.1.2.(1)(b) Comply Comply Comply
Show suites (occupancy term greater than one year) Comply Comply Comply Comply
Portable and re-locatable structures Units manufactured or site constructed prior to Nov. 1, 2016 do not need to comply. Units constructed after this date must comply with Part 3 requirements. Units manufactured or site constructed prior to Nov. 1, 2016 do not need to comply. Units constructed after this date must comply with Part 4 requirements. Units manufactured or site constructed prior to Nov. 1, 2016 do not need to comply. Units constructed after this date must comply with Part 5 requirements.
 
Typically not applicable. Otherwise, rules to follow those for NECB Parts 3, 4, and 5.
 

Related articles
None
 
Effective date
March 1, 2017
Note: The interpretation above represents a consensus interpretation of the NECB document as it applies to most foreseeable applications and situations. It is intended to provide clarity and guidance, but may not be applicable to every condition found in individual projects. For highly irregular or case-specific interpretation, please contact:

Justin Pockar, Energy and Environmental Coordinator
The City of Calgary
justin.pockar@calgary.ca
403-268-2250
403-888-4681
Facebook
Twitter
Website
Copyright © 2016, The City of Calgary, Planning & Development, All rights reserved.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
The City of Calgary - Planning & Development · P.O. Box 2100, Station M · Mail Code #8114 · Calgary, Alberta T2P 2M5 · Canada